Quality Management Plan (QMP)
Qaremy Construction - NSW Solar Farm Project
Document Control
- Document No: QAR-QMP-001
- Revision: A
- Date: October 2025
- Prepared By: QA Manager
- Approved By: Project Manager
1. Project Overview and Scope
1.1 Project Description
The Farm is a 400MW renewable energy facility located in Central West NSW, Australia. The project involves the design, construction, testing, and commissioning of:
- Approximately 1,000,000+ photovoltaic modules
- Single-axis tracking systems
- Inverter stations and transformers
- 33kV underground and overhead electrical reticulation
- 132kV substation and transmission connection
- Access roads, drainage, and site infrastructure
- Operations and maintenance facilities
1.2 Project Location
- Address: [Site Location], Central West NSW
- Local Government Area: [LGA Name]
- Planning Approval: [DA Number and Date]
1.3 Project Duration
- Commencement: [Start Date]
- Practical Completion: [Target Date]
- Construction Duration: Approximately 18-24 months
1.4 Scope of QMS
This Quality Management System applies to all construction, installation, testing, and commissioning activities for the Solar Farm project, including:
- Civil works and site preparation
- Mechanical installations (trackers, mounting structures)
- Electrical installations (LV, MV, HV systems)
- Testing and commissioning activities
- Materials procurement and control
- Subcontractor management
2. Quality Objectives and Key Performance Indicators (KPIs)
2.1 Quality Objectives
- Compliance: Achieve 100% compliance with contractual requirements, Australian Standards, and regulatory approvals
- Defect-Free Delivery: Minimize defects through robust QC processes
- First-Time Quality: Achieve >95% first-time acceptance rate on inspections
- Safety Integration: Zero quality-related safety incidents
- Documentation Excellence: Maintain complete, accurate, and traceable quality records
2.2 Key Performance Indicators
| KPI | Target | Measurement Frequency |
|---|---|---|
| ITP Compliance Rate | >98% | Monthly |
| NCR Closure Within 30 Days | >90% | Monthly |
| First-Time Inspection Pass Rate | >95% | Monthly |
| Document Submittal On-Time Rate | >95% | Monthly |
| Audit Finding Closure Rate | 100% within agreed timeframe | Per audit |
| Supplier Quality Rating | >85% average score | Quarterly |
| Rework Hours as % of Total | <2% | Monthly |
2.3 Quality Cost Management
- Track costs associated with non-conformances, rework, and quality-related delays
- Monthly reporting to project leadership
- Target: Quality costs <1.5% of project value
3. Organizational Structure and Responsibilities
3.1 Quality Organization Chart
Project Manager
|
├── QA Manager (Independent reporting line to Client)
| |
| ├── Lead QC Inspector (Civil)
| ├── Lead QC Inspector (Electrical)
| └── Lead QC Inspector (Mechanical)
|
├── Construction Manager
| |
| ├── Civil Superintendent
| ├── Electrical Superintendent
| └── Mechanical Superintendent
|
└── Document Controller3.2 Roles and Responsibilities
3.2.1 Project Manager
- Overall accountability for project quality
- Approve Quality Management Plan and major procedures
- Ensure adequate resources for quality activities
- Review quality KPI reports and drive improvement
- Interface with client on quality matters
3.2.2 QA Manager
- Develop, implement, and maintain the QMS
- Lead internal audits and management reviews
- Ensure compliance with contractual quality requirements
- Review and approve ITPs and QC procedures
- Manage non-conformance and corrective action processes
- Interface with client QA representatives and certifiers
- Provide independent quality oversight
- Report quality metrics and trends
- Independence: Reports to Project Manager administratively but has direct line to Client for quality issues
3.2.3 Lead QC Inspectors (by discipline)
- Conduct inspections per approved ITPs
- Verify materials compliance prior to installation
- Witness critical hold points and testing activities
- Complete inspection records and checklists
- Identify and document non-conformances
- Coordinate with subcontractors on quality requirements
- Conduct surveillance inspections
- Verify corrective actions are implemented
3.2.4 Construction Manager / Superintendents
- Implement quality requirements in field operations
- Ensure workforce understands quality expectations
- Coordinate with QC inspectors for scheduled inspections
- Support non-conformance investigations
- Ensure subcontractor compliance with quality requirements
3.2.5 Site Engineers
- Perform self-inspections prior to QC inspection
- Coordinate inspection requests
- Maintain as-built records
- Support testing and commissioning activities
3.2.6 Document Controller
- Manage document control system
- Control distribution of quality documents
- Maintain quality records and archives
- Support document submittals to client
- Ensure latest revisions are in use
3.2.7 Subcontractors
- Comply with project QMS requirements
- Provide qualified QC resources
- Submit material certificates and compliance documentation
- Conduct self-inspections before requesting QC inspection
- Respond to non-conformances within required timeframes
4. Quality Standards and Regulatory Requirements
4.1 Quality Management Standards
Primary Standard:
- AS/NZS ISO 9001:2016 - Quality Management Systems - Requirements
The QMS is structured to align with ISO 9001:2016 principles:
- Customer focus
- Leadership and commitment
- Engagement of people
- Process approach
- Improvement
- Evidence-based decision making
- Relationship management
4.2 Australian Standards for Solar Installations
Electrical Standards
- AS/NZS 5033:2021 - Installation and safety requirements for photovoltaic (PV) arrays
- AS/NZS 3000:2018 - Electrical installations (Australian/New Zealand Wiring Rules)
- AS/NZS 4777.1:2016 - Grid connection of energy systems via inverters - Installation requirements
- AS 2067:2016 - Substations and high voltage installations exceeding 1 kV a.c.
- AS/NZS 61439 - Low-voltage switchgear and controlgear assemblies
Civil & Structural Standards
- AS 2870:2011 - Residential slabs and footings
- AS 3600:2018 - Concrete structures
- AS/NZS 1170 - Structural design actions (wind, earthquake loads)
- AS 3798:2007 - Guidelines on earthworks for commercial and residential developments
Testing & Quality Standards
- AS 1012 - Methods of testing concrete
- AS 1289 - Methods of testing soils for engineering purposes
- AS/NZS 3017:2022 - Electrical installations - Verification guidelines
4.3 NSW Regulatory Requirements
Planning & Environmental
- Development Consent conditions (DA [Number])
- NSW Environmental Planning and Assessment Act 1979
- Protection of the Environment Operations Act 1997
- Biodiversity Conservation Act 2016
Work Health & Safety
- Work Health and Safety Act 2011 (NSW)
- Work Health and Safety Regulation 2017
- SafeWork NSW guidelines and codes of practice
- Electrical Safety Act 2002 and Regulations
Heritage & Indigenous
- National Parks and Wildlife Act 1974 (Aboriginal heritage)
- Heritage Act 1977 (European heritage)
- Aboriginal cultural heritage assessment requirements
4.4 Network Connection Requirements
- Australian Energy Market Operator (AEMO) requirements
- Network Service Provider connection agreement
- National Electricity Rules (NER) compliance
4.5 Industry Guidelines
- Clean Energy Council (CEC) Guidelines for Solar Farms
- Smart Energy Council Best Practice Guidelines
- International Electrotechnical Commission (IEC) standards for PV equipment
5. Interface with Client and Regulatory Bodies
5.1 Client Quality Interface
- Weekly quality meetings with client representatives
- Notification of hold points 48 hours in advance
- Submission of inspection records within 24 hours
- Monthly quality performance reports
- Access to quality records and documentation
5.2 Third-Party Certifiers
- Independent verification of critical activities
- Electrical compliance certification
- Structural certification for tracker foundations
- Substation commissioning verification
5.3 Regulatory Authority Inspections
- SafeWork NSW inspections (electrical work)
- Local council inspections (as required)
- EPA environmental compliance audits
6. Quality System Implementation
6.1 Document Hierarchy
Level 1: Quality Management Plan (This Document)
↓
Level 2: Procedures (QC Procedures, ITPs)
↓
Level 3: Work Instructions & Method Statements
↓
Level 4: Forms, Templates, Checklists
↓
Level 5: Quality Records6.2 Training Requirements
All personnel involved in quality activities must complete:
- QMS induction training
- Role-specific quality training
- Relevant Australian Standards awareness
- Tool and equipment calibration training (as applicable)
6.3 Continuous Improvement
- Monthly quality performance reviews
- Lessons learned workshops after major milestones
- Root cause analysis for systemic issues
- Implementation of corrective and preventive actions
7. Document Control and Revisions
| Revision | Date | Description | Prepared By | Approved By |
|---|---|---|---|---|
| A | Oct 2025 | Initial Issue | QA Manager | Project Manager |
8. Appendices
- Appendix A: Quality Organization Chart (Detailed)
- Appendix B: Quality Forms Register
- Appendix C: Training Matrix
- Appendix D: Document Distribution Matrix
- Appendix E: Acronyms and Definitions
END OF DOCUMENT