Quality Management Plan (QMP)

Qaremy Construction - NSW Solar Farm Project

Document Control

  • Document No: QAR-QMP-001
  • Revision: A
  • Date: October 2025
  • Prepared By: QA Manager
  • Approved By: Project Manager

1. Project Overview and Scope

1.1 Project Description

The Farm is a 400MW renewable energy facility located in Central West NSW, Australia. The project involves the design, construction, testing, and commissioning of:

  • Approximately 1,000,000+ photovoltaic modules
  • Single-axis tracking systems
  • Inverter stations and transformers
  • 33kV underground and overhead electrical reticulation
  • 132kV substation and transmission connection
  • Access roads, drainage, and site infrastructure
  • Operations and maintenance facilities

1.2 Project Location

  • Address: [Site Location], Central West NSW
  • Local Government Area: [LGA Name]
  • Planning Approval: [DA Number and Date]

1.3 Project Duration

  • Commencement: [Start Date]
  • Practical Completion: [Target Date]
  • Construction Duration: Approximately 18-24 months

1.4 Scope of QMS

This Quality Management System applies to all construction, installation, testing, and commissioning activities for the Solar Farm project, including:

  • Civil works and site preparation
  • Mechanical installations (trackers, mounting structures)
  • Electrical installations (LV, MV, HV systems)
  • Testing and commissioning activities
  • Materials procurement and control
  • Subcontractor management

2. Quality Objectives and Key Performance Indicators (KPIs)

2.1 Quality Objectives

  1. Compliance: Achieve 100% compliance with contractual requirements, Australian Standards, and regulatory approvals
  2. Defect-Free Delivery: Minimize defects through robust QC processes
  3. First-Time Quality: Achieve >95% first-time acceptance rate on inspections
  4. Safety Integration: Zero quality-related safety incidents
  5. Documentation Excellence: Maintain complete, accurate, and traceable quality records

2.2 Key Performance Indicators

KPITargetMeasurement Frequency
ITP Compliance Rate>98%Monthly
NCR Closure Within 30 Days>90%Monthly
First-Time Inspection Pass Rate>95%Monthly
Document Submittal On-Time Rate>95%Monthly
Audit Finding Closure Rate100% within agreed timeframePer audit
Supplier Quality Rating>85% average scoreQuarterly
Rework Hours as % of Total<2%Monthly

2.3 Quality Cost Management

  • Track costs associated with non-conformances, rework, and quality-related delays
  • Monthly reporting to project leadership
  • Target: Quality costs <1.5% of project value

3. Organizational Structure and Responsibilities

3.1 Quality Organization Chart

Project Manager
    |
    ├── QA Manager (Independent reporting line to Client)
    |       |
    |       ├── Lead QC Inspector (Civil)
    |       ├── Lead QC Inspector (Electrical)
    |       └── Lead QC Inspector (Mechanical)
    |
    ├── Construction Manager
    |       |
    |       ├── Civil Superintendent
    |       ├── Electrical Superintendent
    |       └── Mechanical Superintendent
    |
    └── Document Controller

3.2 Roles and Responsibilities

3.2.1 Project Manager

  • Overall accountability for project quality
  • Approve Quality Management Plan and major procedures
  • Ensure adequate resources for quality activities
  • Review quality KPI reports and drive improvement
  • Interface with client on quality matters

3.2.2 QA Manager

  • Develop, implement, and maintain the QMS
  • Lead internal audits and management reviews
  • Ensure compliance with contractual quality requirements
  • Review and approve ITPs and QC procedures
  • Manage non-conformance and corrective action processes
  • Interface with client QA representatives and certifiers
  • Provide independent quality oversight
  • Report quality metrics and trends
  • Independence: Reports to Project Manager administratively but has direct line to Client for quality issues

3.2.3 Lead QC Inspectors (by discipline)

  • Conduct inspections per approved ITPs
  • Verify materials compliance prior to installation
  • Witness critical hold points and testing activities
  • Complete inspection records and checklists
  • Identify and document non-conformances
  • Coordinate with subcontractors on quality requirements
  • Conduct surveillance inspections
  • Verify corrective actions are implemented

3.2.4 Construction Manager / Superintendents

  • Implement quality requirements in field operations
  • Ensure workforce understands quality expectations
  • Coordinate with QC inspectors for scheduled inspections
  • Support non-conformance investigations
  • Ensure subcontractor compliance with quality requirements

3.2.5 Site Engineers

  • Perform self-inspections prior to QC inspection
  • Coordinate inspection requests
  • Maintain as-built records
  • Support testing and commissioning activities

3.2.6 Document Controller

  • Manage document control system
  • Control distribution of quality documents
  • Maintain quality records and archives
  • Support document submittals to client
  • Ensure latest revisions are in use

3.2.7 Subcontractors

  • Comply with project QMS requirements
  • Provide qualified QC resources
  • Submit material certificates and compliance documentation
  • Conduct self-inspections before requesting QC inspection
  • Respond to non-conformances within required timeframes

4. Quality Standards and Regulatory Requirements

4.1 Quality Management Standards

Primary Standard:

  • AS/NZS ISO 9001:2016 - Quality Management Systems - Requirements

The QMS is structured to align with ISO 9001:2016 principles:

  • Customer focus
  • Leadership and commitment
  • Engagement of people
  • Process approach
  • Improvement
  • Evidence-based decision making
  • Relationship management

4.2 Australian Standards for Solar Installations

Electrical Standards

  • AS/NZS 5033:2021 - Installation and safety requirements for photovoltaic (PV) arrays
  • AS/NZS 3000:2018 - Electrical installations (Australian/New Zealand Wiring Rules)
  • AS/NZS 4777.1:2016 - Grid connection of energy systems via inverters - Installation requirements
  • AS 2067:2016 - Substations and high voltage installations exceeding 1 kV a.c.
  • AS/NZS 61439 - Low-voltage switchgear and controlgear assemblies

Civil & Structural Standards

  • AS 2870:2011 - Residential slabs and footings
  • AS 3600:2018 - Concrete structures
  • AS/NZS 1170 - Structural design actions (wind, earthquake loads)
  • AS 3798:2007 - Guidelines on earthworks for commercial and residential developments

Testing & Quality Standards

  • AS 1012 - Methods of testing concrete
  • AS 1289 - Methods of testing soils for engineering purposes
  • AS/NZS 3017:2022 - Electrical installations - Verification guidelines

4.3 NSW Regulatory Requirements

Planning & Environmental

  • Development Consent conditions (DA [Number])
  • NSW Environmental Planning and Assessment Act 1979
  • Protection of the Environment Operations Act 1997
  • Biodiversity Conservation Act 2016

Work Health & Safety

  • Work Health and Safety Act 2011 (NSW)
  • Work Health and Safety Regulation 2017
  • SafeWork NSW guidelines and codes of practice
  • Electrical Safety Act 2002 and Regulations

Heritage & Indigenous

  • National Parks and Wildlife Act 1974 (Aboriginal heritage)
  • Heritage Act 1977 (European heritage)
  • Aboriginal cultural heritage assessment requirements

4.4 Network Connection Requirements

  • Australian Energy Market Operator (AEMO) requirements
  • Network Service Provider connection agreement
  • National Electricity Rules (NER) compliance

4.5 Industry Guidelines

  • Clean Energy Council (CEC) Guidelines for Solar Farms
  • Smart Energy Council Best Practice Guidelines
  • International Electrotechnical Commission (IEC) standards for PV equipment

5. Interface with Client and Regulatory Bodies

5.1 Client Quality Interface

  • Weekly quality meetings with client representatives
  • Notification of hold points 48 hours in advance
  • Submission of inspection records within 24 hours
  • Monthly quality performance reports
  • Access to quality records and documentation

5.2 Third-Party Certifiers

  • Independent verification of critical activities
  • Electrical compliance certification
  • Structural certification for tracker foundations
  • Substation commissioning verification

5.3 Regulatory Authority Inspections

  • SafeWork NSW inspections (electrical work)
  • Local council inspections (as required)
  • EPA environmental compliance audits

6. Quality System Implementation

6.1 Document Hierarchy

Level 1: Quality Management Plan (This Document)

Level 2: Procedures (QC Procedures, ITPs)

Level 3: Work Instructions & Method Statements

Level 4: Forms, Templates, Checklists

Level 5: Quality Records

6.2 Training Requirements

All personnel involved in quality activities must complete:

  • QMS induction training
  • Role-specific quality training
  • Relevant Australian Standards awareness
  • Tool and equipment calibration training (as applicable)

6.3 Continuous Improvement

  • Monthly quality performance reviews
  • Lessons learned workshops after major milestones
  • Root cause analysis for systemic issues
  • Implementation of corrective and preventive actions

7. Document Control and Revisions

RevisionDateDescriptionPrepared ByApproved By
AOct 2025Initial IssueQA ManagerProject Manager

8. Appendices

  • Appendix A: Quality Organization Chart (Detailed)
  • Appendix B: Quality Forms Register
  • Appendix C: Training Matrix
  • Appendix D: Document Distribution Matrix
  • Appendix E: Acronyms and Definitions

END OF DOCUMENT