Inspection and Test Plan (ITP) - Civil Works

Qaremy Construction - NSW Solar Farm Project

Document Control

  • Document No: QAR-ITP-CIV-001
  • Revision: A
  • Date: October 2025
  • Discipline: Civil Works

1. Purpose and Scope

This Inspection and Test Plan (ITP) defines the inspection and testing requirements for civil works associated with the Solar Farm project.

Scope includes:

  • Site preparation and earthworks
  • Access roads and internal roads
  • Drainage works
  • Tracker foundation piles/footings
  • Inverter station and substation foundations
  • Cable trenches and conduits
  • Site facilities and amenities

2. Inspection Point Definitions

2.1 Hold Point (H)

Work must stop and cannot proceed until the inspection is completed and documented approval is given by the designated party.

Symbol: 🛑 H

2.2 Witness Point (W)

The designated party must be given the opportunity to witness the activity. If they choose not to attend after notification, work may proceed.

Symbol: 👁️ W

2.3 Review Point (R)

Documentation must be submitted for review. Work may proceed while review is in progress unless stated otherwise.

Symbol: 📋 R


3. Inspection Parties

CodePartyRole
SCSubcontractorSelf-inspection
QCQC InspectorContractor quality control
QAQA ManagerClient/independent quality assurance
ENGEngineerEngineer's representative
TPThird PartyIndependent certifier/testing laboratory

4. ITP Table - Site Preparation and Earthworks

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Site Clearance
Pre-clearance surveyHeritage and environmental checkWQA, ENVDA ConditionsClearance approved by environmental consultantSurvey report
Vegetation clearingCompliance with clearing limitsWQC, ENVDA ConditionsWithin approved boundariesSite photos
Topsoil strippingDepth and stockpile locationRQCDA ConditionsMin 100mm depth, designated stockpile areaInspection checklist
Bulk Earthworks
Survey setoutDimensional checkHQC, ENGAS 3798±50mm horizontal, ±25mm verticalSurvey certificate
Stripping depth verificationLevel surveyRQCDesign specsAs per geotechnical reportSurvey report
Compaction - subgradeDensity testingHQC, TPAS 1289.5.8.1≥95% Standard Maximum Dry Density (SMDD)Test certificates
Moisture contentLaboratory testWTPAS 1289.2.1.1Within ±2% of optimum moisture contentTest certificates
Cut/Fill Slopes
Batter slope verificationDimensional checkRQCDesign drawingsWithin design tolerance (typically 1:3)Inspection record
Erosion control measuresVisual inspectionRQCESCPMeasures in place as per ESCPSite photos

5. ITP Table - Access Roads and Internal Roads

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Subgrade Preparation
Survey setoutHorizontal and vertical alignmentHQC, ENGAS 3798Per design drawings ±50mmSurvey certificate
Subgrade compactionField density testHQC, TPAS 1289.5.8.1≥98% SMDDTest certificates (1 per 500m² or as specified)
Subgrade proof rollingHeavy roller testWQCAS 3798No pumping, rutting, or deflectionInspection record
Base Course
Material certificationMaterial source approvalHQAAS 2758.1Complies with spec for grading, plasticityMaterial certificates
Layer thicknessMeasurementRQCSpec drawings±20mm of design thickness (typically 150-200mm)Inspection checklist
Compaction - base courseField density testHQC, TPAS 1289.5.8.1≥98% SMDD (modified)Test certificates (1 per 1000m² min)
Level and gradeSurvey checkWQCDesign drawingsWithin tolerance ±25mmSurvey report
Wearing Course
Material certificationGravel/seal specificationHQAAS 2758.1Complies with wearing course specMaterial certificates
Layer thicknessCore samples or measurementRQCSpec drawingsPer specification (typically 50-75mm)Test results
Compaction - wearing courseField density testHQC, TPAS 1289.5.8.1≥98% SMDDTest certificates
Surface finishVisual and measurementRQCDesign specNo loose material, smooth finishInspection checklist
Final surveyAs-built surveyRENGDesign drawingsWithin toleranceAs-built drawings

Testing Frequency:

  • Compaction tests: Minimum 1 per 500m² for subgrade, 1 per 1000m² for base course
  • Additional tests at location changes or material changes

6. ITP Table - Drainage Works

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Drainage Channels
Survey setoutLine and levelHQCDesign drawings±50mm horizontal, ±25mm verticalSurvey certificate
Excavation dimensionsWidth, depth, batter slopesRQCDesign drawingsPer design specificationInspection checklist
Erosion protectionRock sizing and placementWQCAS 3798, DesignComplies with rock sizing, filter layer requirementsMaterial cert, photos
Culverts
Bedding materialGrading and compactionHQCAS 3725Complies with bedding specTest certificate
Pipe installationLine, grade, joint integrityHQCAS 3725Grade per design (min 0.5%), no deflectionSurvey certificate
Backfill compactionDensity testHQC, TPAS 1289.5.8.1≥95% SMDDTest certificates
Headwalls and endwallsDimensions and finishRQCDesign drawingsPer specificationInspection record

7. ITP Table - Tracker Foundation Piles

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Pre-Installation
Survey setoutGrid layout and elevationHQC, ENGDesign drawings±20mm horizontal positionSurvey certificate
Pile specification reviewPile type, dimensions, steel gradeRQADesign drawings, AS 1163Complies with structural designMaterial certificates
Pile delivery inspectionVisual inspection, quantityRQCPurchase orderNo damage, correct specificationDelivery docket
Pile Installation
Pile verticalityPlumb checkRSCSpec (typically 1:75)Within 1° of verticalInspection checklist
Pile embedment depthMeasurementHQCGeotechnical reportMinimum depth per geotech (typically 1.5-2.5m)Installation log
Torque measurementDrive torque or resistanceHQCGeotechnical reportMinimum torque value (e.g., 8-15 kNm depending on soil)Torque log sheet
Top of pile levelSurveyWQCDesign drawings±25mm from design levelSurvey report
Load Testing
Pile load test (sample)Compressive and lateral load testHTP, ENGAS 2159Per structural design requirementsLoad test certificate
FrequencyTest sample--Geotech reportTypically 1% of piles or min 3 per soil typeTest schedule
Post-Installation
Final alignment checkGrid verificationRQCDesign toleranceRow alignment within ±50mmSurvey report
Pile protectionCorrosion protection verificationRQCSpecificationGalvanizing intact, no damageInspection checklist

Hold Point Note: Pile installation must stop if:

  • Refusal before minimum depth is reached
  • Torque values fall below minimum threshold
  • Pile deviates beyond acceptable tolerance

8. ITP Table - Concrete Foundations (Inverter Stations, Substation)

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Pre-Pour Activities
Survey setoutFoundation location and levelHQC, ENGAS 3600, Design±10mm horizontal, ±5mm verticalSurvey certificate
ExcavationDimensions and base conditionHQC, ENGDesign drawingsCorrect size, firm undisturbed baseInspection checklist
FormworkAlignment, bracing, levelHQCAS 3600Secure, no movement, correct dimensionsFormwork checklist
ReinforcementBar size, spacing, cover, lapsHQCAS 3600Per structural drawings, 50mm cover minRebar inspection form
Reinforcement cleanlinessVisual checkRQCAS 3600Free from loose rust, oil, coatingsInspection record
EmbedmentsAnchor bolts, conduits, insertsHQCDesign drawingsCorrect location ±5mm, securedEmbedment checklist
Concrete Supply
Concrete mix designDesign approvalHQA, ENGAS 1379Approved mix design (typically N32 or N40)Mix design certificate
Delivery docketBatch detailsRQCAS 1379Correct mix, slump, batch timeDelivery dockets
Slump testWorkability checkWQC, TPAS 1012.3.1Within specified range (typically 80-120mm)Slump test record
Concrete Placement
Pour inspectionPlacement method, compactionWQCAS 3600No segregation, proper vibrationPour record
Concrete samplesCompression test cylindersHTPAS 1012.8.16 cylinders minimum per pourSample register
Surface finishLevel and finishRQCSpecificationLevel to tolerance, smooth finishInspection checklist
Post-Pour
CuringCuring method verificationRQCAS 3600Curing compound or wet curing for 7 daysCuring record
Concrete strength testing7-day and 28-day compressive strengthHTPAS 1012.9≥N32 MPa (or as designed) at 28 daysTest certificates
Formwork removalTiming and inspectionRQCAS 3600After sufficient strength gain (min 3 days)Inspection record
As-built surveyFinal dimensions and levelsRQCDesign drawings±10mm toleranceAs-built drawings

Concrete Testing Frequency:

  • Slump test: Each pour or every 50m³
  • Compression samples: Minimum 6 cylinders per pour (test at 7 and 28 days)

9. ITP Table - Cable Trenches and Conduits

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Excavation
Survey setoutTrench alignment and depthHQCDesign drawings±100mm horizontal, ±50mm depthSurvey certificate
Excavation dimensionsWidth, depth, side wallsRQCAS 3000, DesignMin 600mm depth (per AS 3000 for burial)Inspection checklist
Service clearanceUtility location verificationHQC, ENGDial Before You DigNo conflict with existing servicesService location plan
Trench bottom conditionBase preparationRQCAS 3000Free from rocks, debris, firm baseInspection record
Conduit Installation
Conduit material checkMaterial certificationRQAAS/NZS 2053Approved conduit type (PVC, HDPE)Material certificates
Bedding materialSand or approved beddingHQCAS 3000100mm min sand bedding below conduitInspection checklist
Conduit layingAlignment and supportRQCAS 3000Straight runs, adequately supportedInspection record
Warning tape installationMarker tape placementHQCAS 3000Installed 300mm above conduitInspection checklist
Backfill
Initial backfillMaterial and compactionHQCAS 3000Sand to 300mm above conduit, light compactionInspection record
Final backfillCompactionRQCAS 3798Compacted in layers, no voidsInspection checklist
Documentation
As-built surveyTrench route and depthHQCAS 3000Recorded before backfillAs-built drawings
Photographic recordPhotos at key pointsRQC-Clear identification of routePhoto log

10. Inspection Request and Notification

10.1 Notification Requirements

Inspection TypeAdvance Notice Required
Hold Point (H)Minimum 48 hours
Witness Point (W)Minimum 24 hours
Review Point (R)As per document submittal schedule

10.2 Inspection Request Process

  1. Subcontractor completes self-inspection
  2. Request for Inspection (RFI) submitted to QC Inspector
  3. QC Inspector schedules and conducts inspection
  4. QA or third-party notified for Hold/Witness points
  5. Inspection record completed and distributed within 24 hours

11. Non-Conformance Management

If an inspection identifies non-compliance:

  1. Stop work in affected area
  2. Document non-conformance (NCR form)
  3. Investigate root cause
  4. Propose corrective action
  5. Implement correction
  6. Re-inspect before proceeding

12. Testing Laboratory Requirements

All testing must be conducted by NATA-accredited laboratories (National Association of Testing Authorities, Australia).

Required Accreditation:

  • Soil testing: NATA accreditation for AS 1289 series
  • Concrete testing: NATA accreditation for AS 1012 series

13. Quality Records Retention

All inspection and test records shall be retained for minimum 7 years post-project completion or as per contractual requirements.

Records include:

  • Inspection checklists and forms
  • Test certificates
  • Material certificates
  • Survey reports
  • Non-conformance reports
  • Photographic records

14. Revision History

RevisionDateDescriptionPrepared ByApproved By
AOct 2025Initial IssueLead QC Inspector (Civil)QA Manager

END OF DOCUMENT