Inspection and Test Plan (ITP) - Electrical Works

Qaremy Construction - NSW Solar Farm Project

Document Control

  • Document No: QAR-ITP-ELE-001
  • Revision: A
  • Date: October 2025
  • Discipline: Electrical Works

1. Purpose and Scope

This Inspection and Test Plan defines the inspection and testing requirements for electrical works associated with the Solar Farm project.

Scope includes:

  • PV module installation
  • DC cabling and terminations
  • Inverters and inverter stations
  • MV transformers
  • LV/MV switchgear
  • 33kV underground and overhead cabling
  • 132kV substation equipment
  • Earthing and lightning protection
  • SCADA and monitoring systems
  • Testing and commissioning

2. Applicable Standards

  • AS/NZS 5033:2021 - Installation and safety requirements for photovoltaic arrays
  • AS/NZS 3000:2018 - Electrical installations (Wiring Rules)
  • AS/NZS 4777.1:2016 - Grid connection of energy systems via inverters
  • AS/NZS 3017:2022 - Electrical installations - Verification guidelines
  • AS 2067:2016 - Substations and high voltage installations
  • AS/NZS 61439 series - Low-voltage switchgear and controlgear assemblies
  • IEC 62446 - Grid connected PV systems - Minimum requirements for documentation, commissioning tests and inspection

3. Inspection Point Definitions

SymbolTypeDefinition
🛑 HHold PointWork must stop until inspection completed and approval given
👁️ WWitness PointInspector must be given opportunity to witness
📋 RReview PointDocumentation reviewed, work may proceed during review

4. ITP Table - PV Module Installation

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Pre-Installation
Module delivery inspectionVisual inspection, quantity verificationRQCAS/NZS 5033No visible damage, datasheet matches orderDelivery checklist
Module data verificationDatasheet and certification reviewHQAAS/NZS 5033, IEC 61215Valid IEC certification, meets design specificationProduct certificates
Module flash test reportFactory test dataRQAIEC 61215Power rating within tolerance (typically +/-3%)Flash test reports
Module storageStorage conditions checkRQCAS/NZS 5033Protected from weather, off ground, stable stackingInspection record
Installation
Mounting clamp installationTorque verificationWQCAS/NZS 5033, OEM specTorque per specification (typically 8-12 Nm)Torque log (sample 10%)
Module placementOrientation and alignmentRQCDesign drawingsCorrect orientation, aligned in arrayInspection checklist
Module serial number recordingSerial number captureRQCAS/NZS 5033All serial numbers recorded per stringModule register
Electrical Connections
DC connector inspectionConnector type and conditionHQCAS/NZS 5033IP68 rated, no damage, positive click connectionConnector checklist
String polarity checkPolarity verificationHQCAS/NZS 5033Correct polarity confirmed before parallelingPolarity test record
String open-circuit voltageVoc measurementHQC, TPAS/NZS 5033Within 5% of calculated Voc (considering temperature)String test sheet
String short-circuit currentIsc measurementWQCAS/NZS 5033Within 10% of expected IscString test sheet
String insulation resistanceInsulation test (DC+ and DC- to earth)HQC, TPAS/NZS 5033>1 MΩ (test at 500V DC)Insulation test certificate
String continuityContinuity checkWQCAS/NZS 5033Continuous circuit verifiedTest record
Post-Installation
Final visual inspectionPhysical condition checkRQCAS/NZS 5033No damage, all modules secure, cleanInspection checklist
String labelingLabel verificationRQCAS/NZS 5033All strings clearly labeled per numbering systemPhoto evidence
As-built documentationString layout confirmationRQCProject requirementsMatches as-installed configurationAs-built drawings

Testing Frequency:

  • Torque verification: 10% sample per array
  • Voc/Isc: 100% of strings
  • Insulation resistance: 100% of strings

5. ITP Table - DC Cabling and Combiner Boxes

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
DC Cabling
Cable material certificationMaterial certificates reviewHQAAS/NZS 5033UV resistant, rated for 1500V DC, compliant with AS/NZS 5000.1Cable certificates
Cable installationInstallation method checkRQCAS/NZS 5033Correct routing, support, no sharp bends (min radius >10× cable diameter)Inspection checklist
Cable sizing verificationConductor size checkRQCAS/NZS 5033Per design calculations, voltage drop ❤️%Cable schedule
Cable terminationsVisual inspectionWQCAS/NZS 5033Proper crimping, correct ferrules, no exposed conductorTermination checklist
Cable gland installationIP rating verificationRQCAS/NZS 5033IP68 rating maintained, properly sealedInspection record
Combiner Boxes / DC Switchboards
Equipment certificationType approvalHQAAS/NZS 5033Compliant with AS/NZS 61439, IP rating suitable (typically IP65)Equipment certificates
Installation locationMounting and accessibilityRQCAS/NZS 5033Secure mounting, accessible, correct labelingInspection checklist
Fuse ratings verificationFuse/breaker sizing checkHQCAS/NZS 5033Rated for string Isc × 1.25 minimumFuse schedule
Polarity checkDC polarity verificationHQCAS/NZS 5033Correct polarity throughoutPolarity test sheet
Insulation resistance testInsulation testHQC, TPAS/NZS 5033>1 MΩ at 500V DC (each circuit to earth and circuit-to-circuit)Test certificate
Earth continuity testEarth bonding verificationHQCAS/NZS 3000<0.5Ω resistance to main earthEarth test certificate

6. ITP Table - Inverters and Inverter Stations

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Pre-Installation
Inverter certificationType test certificatesHQAAS/NZS 4777.2, IEC 62109Valid certification, meets grid connection requirementsProduct certificates
Equipment receipt inspectionPhysical inspection on deliveryRQCManufacturer specsNo transit damage, complete accessoriesDelivery checklist
Foundation/mounting verificationCivil/structural inspectionHQCDesign drawingsFoundation level and dimensions correctSurvey certificate
Installation
Inverter mountingAlignment and fixingRQCOEM manualLevel, secure mounting per manufacturer instructionsInspection checklist
DC connectionsTermination inspectionHQCAS/NZS 5033Correct polarity, torque per spec, no damageTermination record
AC connectionsTermination inspectionHQCAS/NZS 3000Phase sequence correct, torque verifiedTermination record
Communication cablingNetwork connectionsRQCOEM manualCorrect cable type, properly terminatedInspection checklist
Testing
DC input insulation testInsulation resistanceHTPAS/NZS 5033>1 MΩ at 500V DCTest certificate
AC output insulation testInsulation resistanceHTPAS/NZS 3000>1 MΩ at 500V ACTest certificate
Earth continuityMain earth connectionHQC, TPAS/NZS 3000<0.5Ω to main earthTest certificate
Polarity and phase rotationAC output verificationHQC, TPAS/NZS 3000Correct phase sequence (A-B-C / R-Y-B)Test certificate
Protection settingsSettings verificationHENG, TPAS/NZS 4777.2Per network connection agreementSettings sheet
Functional testingOperation verificationWTP, ENGAS/NZS 4777.2Start-up, normal operation, alarms testedFunctional test report
Commissioning
String-to-inverter assignmentLogical connection checkRQCDesign drawingsCorrect strings connected to correct invertersConnection schedule
Initial energizationFirst power-upHTP, ENGOEM manualNo faults, normal operationCommissioning log
Performance testingPower output verificationWTP, ENGIEC 62446Output within expected range for irradiancePerformance test report
Grid protection testsAnti-islanding, over/under voltage, frequencyHTP, ENGAS/NZS 4777.2Trips within required time limitsProtection test certificate

7. ITP Table - MV Transformers and Switchgear

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Transformer (LV/MV)
Factory acceptance testsReview of factory test reportsHQA, ENGAS 60076, IEC 60076All routine tests passedFactory test certificates
Delivery inspectionPhysical condition checkRQCAS 60076No damage, oil level correct, accessories completeInspection checklist
Installation alignmentMounting and levelingRQCOEM manualLevel within tolerance, secure mountingSurvey report
Oil sampling and testingOil dielectric strengthHTPAS 1767.1>50 kV breakdown voltageOil test certificate
Winding resistanceDC resistance measurementHTPAS 60076Within manufacturer tolerance (typically ±2%)Test certificate
Insulation resistanceMegger testHTPAS 60076>1000 MΩ (HV-LV, HV-E, LV-E)Test certificate
Voltage ratio testTurns ratio verificationHTPAS 60076Within ±0.5% of nameplateTest certificate
Vector group verificationWinding configurationHTPAS 60076Matches nameplate (e.g., Dyn11)Test certificate
MV Switchgear
Equipment certificationType test certificatesHQAAS 62271, IEC 62271Valid type test certificatesProduct certificates
Delivery and storageCondition on receiptRQCAS 62271No damage, stored per manufacturer requirementsInspection checklist
InstallationAlignment and fixingRQCOEM manualLevel, securely fixed, clearances maintainedInspection checklist
Cable terminationsTermination inspectionHQC, TPAS 2067Correct termination kit, torque verified, no voidsTermination checklist
Insulation resistanceMegger testHTPAS 2067>1000 MΩ at 5000V DCTest certificate
HV withstand testHigh voltage AC testHTPAS 62271No breakdown at test voltage (typically 95 kV for 33kV equipment)Test certificate
Circuit breaker operationMechanical operation testHTPAS 62271Correct operation (open/close times within spec)Test certificate
Protection relay settingsSettings verificationHENG, TPProtection studyPer approved protection coordination studySettings sheets
Earthing and Bonding
Earth grid installationVisual inspectionWQCAS 2067Correctly installed per designInspection checklist
Earth grid resistanceEarth resistance testHTPAS 2067<1Ω (or per design requirement)Test certificate
Earthing conductor sizingPhysical verificationRQCAS 2067Minimum 70mm² copper (or per design)Inspection checklist
Bonding connectionsVisual and physical checkRQCAS 2067All metalwork bonded, secure connectionsBonding checklist

8. ITP Table - HV Cabling (33kV Underground)

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Cable Supply
Cable certificationMaterial certificatesHQAAS/NZS 1429.1Type tested, meets specification (XLPE, 19/33kV)Cable certificates
Cable drum inspectionCondition on deliveryRQCAS 1026No damage, correct labeling, drum rotation checkDelivery checklist
Cable storageStorage conditionsRQCAS 1026Protected from weather, drums secureInspection record
Cable Installation
Trench/conduit preparationCivil works sign-offHQCITP-CIV-001Trenches/conduits ready per civil ITPCivil completion cert
Cable pulling setupInstallation method checkWQCAS 1026Correct equipment, tension monitoring, no sharp bendsInstallation checklist
Cable pullingTension and bend radius monitoringWQCAS 1026Tension <70% max rating, bend radius >15× cable diameterPulling log
Cable identificationCable labelingRQCAS 1026All cables clearly labeled per numbering systemPhoto evidence
Cable Jointing and Terminations
Jointer qualificationsCertification checkHQAAS/NZS 3017Valid jointing certification for voltage levelQualification certificates
Work environmentJointing area inspectionWQCAS 1026Clean, dry, temperature controlled (10-30°C typically)Environmental log
Cable preparationCable sheath strippingWQC, TPOEM instructionsClean, no damage to insulation, correct dimensionsPreparation checklist
Joint/termination installationInstallation process witnessHQC, TPOEM instructionsPer manufacturer instructions, no contaminationInstallation log
Joint/termination resistanceDC resistance checkWTPAS 1026<1 mΩ per jointTest certificate
Testing
Insulation resistanceMegger test (phase-to-earth and phase-to-phase)HTPAS/NZS 3017>1000 MΩ at 5000V DCTest certificate
HV withstand testAC voltage testHTP, ENGAS/NZS 3017No breakdown at 95 kV (for 33kV cable) for 1 minuteTest certificate
Partial discharge testPD measurementWTPIEC 60270<5 pC at 1.5 × Uo (optional but recommended)Test certificate
Tan delta testDissipation factorWTPIEEE 400Within acceptable range (optional)Test certificate
Sheath integrity testSheath voltage testHTPAS 1026No breakdown at 4 kV DC for 1 minuteTest certificate
Post-Installation
Cable identification tagsTagging verificationRQCAS 2067All cables tagged at accessible pointsPhoto evidence
As-built surveyCable route recordingHQCAS 2067Accurate as-built records before backfillAs-built drawings
BackfillingBackfill inspectionRQCITP-CIV-001Per civil ITP requirementsCivil inspection record

Critical Hold Point: All HV testing must be witnessed by qualified electrical testing technician and approved by Engineer before energization.


9. ITP Table - 132kV Substation (Primary Plant)

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Power Transformer (132/33kV)
Factory acceptance testsReview FAT reportsHENG, QAAS 60076All type and routine tests passedFAT certificates
Transport and deliveryCondition on arrivalRQCAS 60076No damage, nitrogen pressure maintainedInspection checklist
InstallationFoundation and alignmentWENGDesign drawingsLevel, aligned, torque on foundationsInstallation record
Oil processingOil filtering/degassingWTPAS 1767.1Moisture <10 ppm, breakdown >60 kVOil test certificate
Winding resistanceDC resistance testHTPAS 60076Per FAT values ±2%Test certificate
Insulation resistanceMegger test (10 kV)HTPAS 60076>10,000 MΩTest certificate
Voltage ratioTurns ratio all tapsHTPAS 60076Per nameplate ±0.5%Test certificate
Vector groupPhase displacement checkHTPAS 60076Matches nameplateTest certificate
Frequency response analysis (FRA)Winding integrity checkWTPIEC 60076-18Compared to factory baseline, <2% deviationFRA report
Dissolved gas analysisOil quality testHTPAS 1767.1No abnormal gases indicating faultsDGA report
132kV Circuit Breakers
Type test certificatesCertificate reviewHQA, ENGAS 62271Valid type tests for breaking capacityProduct certificates
SF6 gas qualityGas moisture and purityHTPIEC 60480Dew point <-40°C, purity >97%Gas test certificate
Contact resistanceMicro-ohm testHTPAS 62271<100 µΩ per poleTest certificate
Insulation resistanceMegger testHTPAS 62271>10,000 MΩ at 10 kVTest certificate
HV withstand testAC voltage testHTPAS 62271230 kV for 1 minute (for 132kV equipment)Test certificate
Timing testsOperation timingHTPAS 62271Opening/closing times per manufacturer specTest certificate
Trip circuit verificationProtection trip testHTP, ENGProtection designCorrect trip operation from all protection relaysTest certificate
132kV Disconnectors
Mechanical operationOperation testHTPAS 62271Smooth operation, correct alignmentTest certificate
Contact resistanceMicro-ohm testHTPAS 62271<100 µΩ per poleTest certificate
Insulation resistanceMegger testHTPAS 62271>10,000 MΩ at 10 kVTest certificate
Protection and Control
Protection relay settingsSettings reviewHENGProtection studyPer approved coordination studySettings sheets
Protection relay testingSecondary injection testHTPRelay manualCorrect operation for all functionsTest certificates
SCADA integrationCommunications testWTPSCADA specAll signals verified, control functions testedSCADA test report

10. ITP Table - Earthing and Lightning Protection

ActivityInspection/TestTypePartyReference StandardAcceptance CriteriaRecords
Earth Grid Installation
Material certificationConductor and exothermic weld materialHQAAS 2067Complies with AS/NZS 4431Material certificates
Conductor sizingPhysical verificationRQCAS 2067Minimum 70mm² copper (or per design)Inspection checklist
Grid layoutAs-installed verificationWQCDesign drawingsPer earthing design layoutSurvey report
Exothermic weldingWeld quality inspectionWQCAS 2067Complete fusion, no cracks, correct moldWeld log (100% visual)
Earth electrode installationDepth and spacingRQCAS 2067Per design (typically 3-4.5m depth)Installation record
Earth Testing
Soil resistivity testFour-point testHTPAS 2067For design verificationTest certificate
Earth grid resistanceFall-of-potential testHTPAS 2067<1Ω (or per design requirement)Test certificate
Touch and step potentialPotential gradient measurementWTPAS 2067Within safe limits per AS 2067Test certificate
Lightning Protection
Air terminal installationHeight and locationRQCAS/NZS 1768Per protection zone calculationInspection checklist
Down conductor installationRouting and fixingRQCAS/NZS 1768Direct routes, secure fixing, correct spacingInspection checklist
Surge arrestor installationConnection and ratingHQCAS 1768, AS 4768Correct voltage rating, proper installationInstallation checklist
Lightning conductor continuityEnd-to-end resistanceHTPAS 1768<1Ω from air terminal to earthTest certificate

11. Pre-Energization Checklist

Before any electrical circuit can be energized, the following must be completed and approved:

  • [ ] All installation ITPs completed with no open items
  • [ ] All testing completed and certificates submitted
  • [ ] Insulation resistance tests passed
  • [ ] Earth testing completed and acceptable
  • [ ] Protection settings approved
  • [ ] Lockout/tagout procedures established
  • [ ] Energization procedure approved
  • [ ] Electrical safety risk assessment completed
  • [ ] Electrical workers hold appropriate licenses (ESA/contractor license)
  • [ ] Client/Engineer approval to energize obtained

Hold Point: Energization authority must be obtained from Engineer's Representative before any circuit is energized.


12. Electrical Licensing Requirements (NSW)

All electrical work must be performed by appropriately licensed personnel:

  • Electrical Contractor License: Required for electrical business
  • Electrical Worker License: Required for individual workers
  • HV Authorization: Additional qualification required for work >1kV

Verify licenses before commencement and maintain license register.


13. Testing Frequency Summary

Test TypeFrequency
String Voc/Isc100% of strings
String insulation resistance100% of strings
Module torque check10% sample per array
Cable insulation resistance100% of circuits
Earth continuity100% of circuits
HV cable withstand test100% of cables
Transformer routine tests100% of units
Protection relay tests100% of relays
Earth grid resistanceOnce per grid, re-test after modifications

14. Quality Records Retention

All electrical inspection and test records shall be retained for minimum 7 years or life of asset (whichever is longer) as per AS/NZS 3000 and electrical safety regulations.


15. Revision History

RevisionDateDescriptionPrepared ByApproved By
AOct 2025Initial IssueLead QC Inspector (Electrical)QA Manager

END OF DOCUMENT