QC Procedure: Material Receiving and Verification

Qaremy Construction - NSW Solar Farm Project

Document Control

  • Document No: QAR-QCP-001
  • Revision: A
  • Date: October 2025

1. Purpose

This procedure defines the process for receiving, inspecting, and verifying materials delivered to the Solar Farm project site to ensure they meet specification requirements before installation.


2. Scope

This procedure applies to all materials delivered to site including:

  • PV modules
  • Electrical equipment (inverters, transformers, switchgear, cables)
  • Mechanical equipment (trackers, mounting structures)
  • Civil materials (concrete, reinforcing steel, aggregates)
  • Consumables and accessories

3. Responsibilities

RoleResponsibility
QC InspectorConduct material inspections, verify documentation, approve/reject materials
Site EngineerCoordinate deliveries, provide access, support inspections
Document ControllerRecord and file material certificates and inspection records
Warehouse/LogisticsManage storage areas, track inventory, coordinate deliveries
SubcontractorsNotify of deliveries, provide documentation, address non-conformances

4. Procedure

4.1 Pre-Delivery Requirements

Step 1: Delivery Notification

  • Supplier/subcontractor must provide 48-hour advance notice of delivery
  • Notification must include:
    • Expected delivery date and time
    • Material description and quantity
    • Purchase order number
    • Delivery vehicle details

Step 2: Documentation Requirements Prior to delivery, the following documents must be submitted for review:

Material TypeRequired Documentation
PV Modules- Product datasheet
- IEC 61215/61730 certificates
- Flash test reports (Voc, Isc, Pmax)
- Warranty certificates
Electrical Equipment- Product certificates
- Factory test reports
- Type test certificates
- Compliance with Australian Standards
Cables- Material certificates
- Test certificates (AS/NZS 1429, AS/NZS 5000)
- Continuous length certificates
Steel/Structural- Mill test certificates (material grade)
- Galvanizing certificates (Z275 minimum)
- Traceability documentation
Concrete- Mix design approval
- Materials certificates (cement, aggregates)
- Batch plant certification
Fasteners- Material certificates (bolt grade)
- Compliance certificates (AS 1252)

Step 3: Storage Area Preparation

  • Ensure adequate storage space is available
  • Storage area must be suitable for material type (weather protection if required)
  • Clear access for delivery vehicles

4.2 Delivery Inspection

Step 1: Initial Visual Check Upon arrival, conduct initial inspection:

Vehicle condition: Check for damage to delivery vehicle that may indicate rough transport
Packaging integrity: Inspect for damaged packaging, water ingress, or compromised protection
Security seals: Verify manufacturer seals are intact (if applicable)
Labeling: Check that packages are correctly labeled with product identification

Step 2: Documentation Check Verify the following documents are provided with delivery:

  • ✅ Delivery docket/packing list
  • ✅ Purchase order reference
  • ✅ Material certificates (or submittal reference)
  • ✅ Test certificates (as required by specification)
  • ✅ Batch records (for concrete deliveries)
  • ✅ Warranty cards (for equipment)

Step 3: Quantity Verification

  • Count items delivered and compare to delivery docket
  • For bulk materials, verify volumes/weights against documentation
  • Record any discrepancies immediately
  • Note: Detailed inventory may occur during offloading

Step 4: Physical Inspection

Conduct visual inspection appropriate to material type:

PV Modules

  • ✓ No visible cracks in cells or glass
  • ✓ No delamination or discoloration
  • ✓ Frame is straight, no bending or damage
  • ✓ Junction box intact and sealed
  • ✓ Cables and connectors undamaged
  • ✓ Serial numbers visible and recorded
  • ✓ Inspect sample (minimum 5% of delivery or 10 modules, whichever is greater)

Electrical Equipment (Inverters, Transformers, Switchgear)

  • ✓ No physical damage to enclosures
  • ✓ No dents, scratches, or corrosion
  • ✓ Nameplate data matches purchase order
  • ✓ Accessories and loose items present
  • ✓ Ventilation openings clear
  • ✓ For oil-filled equipment: check oil level and seals

Cables

  • ✓ Drum intact, no damage
  • ✓ Cable end sealed and protected
  • ✓ Drum rotates freely (check for transport damage to core)
  • ✓ Labels match specification (conductor size, voltage rating, length)
  • ✓ Continuous length certification provided (no joints in drum)

Structural Steel

  • ✓ No significant bending or deformation
  • ✓ Galvanizing intact, no large areas of damage
  • ✓ Correct sections and lengths (sample check)
  • ✓ Material identification markings visible
  • ✓ Bundled securely for storage

Concrete (Ready-Mix Delivery)

  • ✓ Delivery docket shows correct mix design reference
  • ✓ Time since batching <90 minutes (or per mix design)
  • ✓ Slump test conducted (AS 1012.3.1)
  • ✓ Compression test samples taken (AS 1012.8.1)
  • ✓ Temperature recorded (if specified)

4.3 Acceptance Decision

Accept:

  • Material meets specification requirements
  • Documentation complete and compliant
  • No significant damage or non-conformance
  • Sign delivery docket "Accepted"
  • Complete Material Receiving Inspection Report (Form QF-001)
  • Allow offloading to designated storage area

Conditional Accept:

  • Minor discrepancies that do not affect material fitness
  • Missing documentation that can be provided within agreed timeframe
  • Mark delivery docket "Conditionally Accepted - pending [specify]"
  • Material may be offloaded to quarantine area (clearly marked)
  • Issue Non-Conformance Report (NCR) if necessary
  • Material released from quarantine only when conditions satisfied

Reject:

  • Significant damage affecting material fitness for use
  • Material does not meet specification
  • Critical documentation missing or non-compliant
  • Mark delivery docket "Rejected - [reason]"
  • Material must not be offloaded OR offloaded to rejection area
  • Issue Non-Conformance Report (NCR)
  • Notify supplier immediately
  • Coordinate return/replacement with procurement team

4.4 Offloading and Storage

Step 1: Offloading

  • Use appropriate lifting equipment (per manufacturer requirements)
  • Follow safe work method statements
  • QC Inspector to witness offloading for sensitive equipment
  • Check for damage during offloading process

Step 2: Storage Location Materials must be stored in appropriate areas:

MaterialStorage Requirements
PV Modules- Under cover or weather-protected
- Stored vertically or on edge (never flat in stacks >6 high)
- On pallets or raised platform (not on ground)
- Protected from mechanical damage
Electrical Equipment- Under cover in clean, dry area
- Protected from weather and contamination
- Maintained in manufacturer packaging until installation
- Temperature controlled if specified
Cables (on drums)- Can be stored outdoors if drum ends sealed
- Drums chocked to prevent rolling
- Protected from UV if long-term storage (>3 months)
Structural Steel- Can be stored outdoors
- On timber bearers to keep off ground
- Bundled securely
- Segregated by type/size
Fasteners- Dry, covered storage
- Segregated by type and grade
- Protected from contamination

Step 3: Identification and Traceability

  • Apply project identification labels/tags
  • Record storage location in material register
  • Maintain traceability to certificates and purchase orders
  • Segregate different material batches/lots

Step 4: Quarantine and Rejection Areas

  • Clearly marked "QUARANTINE - DO NOT USE" or "REJECTED"
  • Physically separated from accepted materials
  • Access controlled (authorized personnel only)
  • Materials tracked until issue resolved or removed from site

4.5 Documentation and Records

Step 1: Complete Material Receiving Inspection Report (Form QF-001) Record the following information:

  • Date and time of delivery
  • Supplier/manufacturer name
  • Material description
  • Quantity received
  • Purchase order number
  • Delivery docket number
  • Documentation received (checklist)
  • Inspection results (Accept/Conditional/Reject)
  • Inspector name and signature
  • Storage location

Step 2: File Documentation

  • Submit to Document Controller within 24 hours
  • Filed in project document management system
  • Linked to purchase order and material certificates

Step 3: Update Material Register

  • Record material receipt in project tracking system
  • Update inventory quantities
  • Flag any materials in quarantine or rejected

Step 4: Issue Non-Conformance Report (If Required)

  • Complete NCR form (Form QF-002) for rejected or conditional materials
  • Distribute to QA Manager, Project Manager, and relevant parties
  • Track NCR to closure

5. Inspection Checklists

5.1 PV Module Inspection Checklist

ItemCheckPass/FailComments
Packaging intactNo damage to packaging
Quantity matches delivery docketCount verified
Product datasheet providedDocumentation present
IEC certificates providedCertification verified
Flash test reports providedTest data present
Glass surfaceNo cracks or damage
CellsNo cracks or discoloration
FrameStraight, no bending
Junction boxIntact and sealed
Cables and connectorsNo damage, correct type
Serial numbersVisible and recorded
Labels and markingsPresent and legible

Sample Size: Minimum 5% or 10 modules (whichever is greater)
Inspector: _________________ Date: __________ Signature: __________


5.2 Electrical Equipment Inspection Checklist

ItemCheckPass/FailComments
Packaging conditionNo damage to packaging/crate
Equipment serial numberMatches documentation
Nameplate dataMatches specification
Factory test reportsProvided and reviewed
Type test certificatesProvided (if required)
Visual inspection - externalNo damage to enclosure
Visual inspection - internalNo damage visible (if accessible)
Loose components/accessoriesAll items present per packing list
Manuals and documentationProvided
Warranty informationProvided

Inspector: _________________ Date: __________ Signature: __________


5.3 Cable Inspection Checklist

ItemCheckPass/FailComments
Drum conditionIntact, rotates freely
Cable end protectionSealed and protected
Drum label informationMatches specification
Cable type and sizeCorrect per purchase order
Continuous length certificateProvided
Material certificatesProvided (conductor, insulation)
Test certificatesProvided (AS/NZS standards)
Drum lengthMatches certificate
Visual cable inspectionNo visible damage

Inspector: _________________ Date: __________ Signature: __________


6. Material Certification Requirements

6.1 Critical Materials Requiring Certification Before Use

Materials must not be installed until the following certificates are verified and approved:

MaterialRequired CertificatesApproval Authority
PV ModulesIEC 61215, IEC 61730, Flash test reportsQA Manager
InvertersAS/NZS 4777.2 compliance, Factory test reportsQA Manager, Engineer
TransformersAS 60076 routine tests, Oil testsEngineer
HV CablesAS/NZS 1429 compliance, Continuous length certQA Manager
Structural SteelMill test certs, Galvanizing certsQA Manager
ConcreteMix design approval, Materials certsEngineer
Fasteners (critical)Material grade certificatesQA Manager

7. Non-Conformance Management

7.1 Types of Non-Conformances

Category 1: Critical (Reject)

  • Material does not meet specification
  • Significant damage affecting fitness for use
  • Missing critical safety certifications
  • Action: Material rejected and returned to supplier

Category 2: Major (Conditional)

  • Minor damage that can be repaired
  • Documentation incomplete but can be rectified
  • Quantity discrepancy
  • Action: Issue NCR, quarantine until resolved

Category 3: Minor (Note)

  • Cosmetic damage not affecting function
  • Administrative errors on documents
  • Action: Note on inspection report, may not require NCR

7.2 Non-Conformance Process

  1. Identify non-conformance during inspection
  2. Mark material and move to quarantine area (if accepted on site)
  3. Issue Non-Conformance Report (NCR Form QF-002)
  4. Notify supplier and procurement team immediately
  5. Propose corrective action (repair, replace, return)
  6. Obtain approval for proposed action from Engineer/QA Manager
  7. Implement corrective action
  8. Re-inspect material
  9. Close NCR when resolved
  10. Update material status in register

8. Material Handling and Preservation

During storage, periodic condition checks must be performed:

MaterialCheck FrequencyWhat to Check
PV ModulesWeeklyPackaging integrity, moisture ingress, physical damage
Electrical EquipmentWeeklyProtection maintained, no corrosion, seals intact
Cables (drums)FortnightlyEnd seals intact, no water on drum, drum condition
Structural SteelMonthlyGalvanizing condition, moisture/corrosion, bundling intact

Any deterioration discovered during storage checks must be documented and addressed.


9. References

  • AS/NZS ISO 9001:2016 - Quality Management Systems
  • Project specifications and technical requirements
  • Supplier/manufacturer delivery requirements
  • QAR-QMP-001 - Quality Management Plan
  • Form QF-001 - Material Receiving Inspection Report
  • Form QF-002 - Non-Conformance Report

10. Attachments

  • Form QF-001: Material Receiving Inspection Report
  • Form QF-002: Non-Conformance Report
  • Material Certification Register Template

11. Revision History

RevisionDateDescriptionPrepared ByApproved By
AOct 2025Initial IssueQA ManagerProject Manager

END OF DOCUMENT