QC Procedure - Non-Conformance Reporting and Corrective Action

Qaremy Construction - NSW Solar Farm Project

Document Control

  • Document No: QAR-QCP-002
  • Revision: A
  • Date: October 2025

1. Purpose

This procedure establishes the process for identifying, documenting, investigating, and resolving non-conformances to prevent recurrence and drive continuous improvement.


2. Scope

This procedure applies to all non-conformances identified during the NSW Solar Farm project, including:

  • Material non-conformances (defective, damaged, or incorrect materials)
  • Installation non-conformances (workmanship defects, incorrect installation)
  • Testing non-conformances (failed tests, out-of-tolerance results)
  • Documentation non-conformances (missing records, incorrect documentation)
  • Process non-conformances (procedure violations)

3. Definitions

Non-Conformance (NC): A deviation from specified requirements, standards, procedures, or approved documentation.

Non-Conformance Report (NCR): A formal document that records the details of a non-conformance and tracks its resolution.

Corrective Action: Action taken to eliminate the cause of a detected non-conformance to prevent recurrence.

Preventive Action: Action taken to eliminate the cause of a potential non-conformance to prevent occurrence.

Root Cause Analysis: Systematic investigation to identify the fundamental reason a non-conformance occurred.


4. Non-Conformance Categories

4.1 Classification by Severity

CategoryDescriptionExamplesImpact
CriticalSignificant safety risk or major specification violation- Electrical safety violation
- Structural defect
- Missing critical certification
Work must stop immediately in affected area
MajorSignificant quality issue affecting performance or compliance- Failed insulation test
- Installation out of tolerance
- Incorrect material used
Work in affected area cannot proceed
MinorQuality issue with limited impact, can be easily corrected- Missing label
- Minor cosmetic damage
- Documentation error
May continue with approved concession

4.2 Classification by Type

TypeDescription
Material NCDefective, damaged, or non-compliant materials
Installation NCWorkmanship defects or incorrect installation methods
Testing NCFailed tests or out-of-specification results
Documentation NCMissing, incorrect, or incomplete records
Process NCFailure to follow approved procedures or plans

5. Responsibilities

RoleResponsibility
Anyone on SiteCan identify and report non-conformances
QC InspectorIdentify, document, and issue NCRs; verify corrective actions
QA ManagerReview and approve NCRs; approve corrective actions; trend analysis
Construction ManagerInvestigate root cause; propose corrective actions; implement corrections
Engineer's RepresentativeReview and approve critical NCRs and proposed corrective actions
SubcontractorsRespond to NCRs; implement corrective actions; prevent recurrence

6. Procedure

6.1 Identification and Reporting

Step 1: Identify Non-Conformance

Non-conformances may be identified through:

  • Routine inspections and QC checks
  • Testing and commissioning activities
  • Material receiving inspections
  • Internal audits
  • Client observations
  • Self-reporting by workers or subcontractors
  • Third-party inspections

Step 2: Immediate Actions

Upon identifying a non-conformance:

Stop affected work (if critical or major)
Isolate non-conforming work/materials (mark with tags or barriers)
Notify QC Inspector immediately (within 4 hours for critical, 24 hours for others)
Take photos (clear evidence of the non-conformance)
Secure the area (prevent further work or contamination)

Step 3: Initial Notification

For critical non-conformances:

  • Notify QA Manager immediately
  • Notify Construction Manager
  • Notify Engineer's Representative (if required by contract)
  • Issue verbal notification followed by written NCR within 4 hours

6.2 Documentation

Step 1: Complete Non-Conformance Report (NCR Form QF-002)

The QC Inspector completes the NCR with the following information:

Section A: NCR Details

  • NCR Number: QAR-NCR-[Sequential Number]
  • Date Raised
  • Raised By (Name and company)
  • Location (specific site location)
  • Discipline (Civil/Electrical/Mechanical)

Section B: Non-Conformance Description

  • Category (Critical/Major/Minor)
  • Type (Material/Installation/Testing/Documentation/Process)
  • Detailed description of non-conformance
  • Reference documents (ITP, specification, drawing number)
  • Requirement (what should have been done)
  • Actual condition (what was found)
  • Photos attached (photo reference numbers)
  • Quantity affected (e.g., "5 trackers," "50m of cable")

Section C: Responsible Party

  • Subcontractor/Supplier name
  • Representative name and contact

Step 2: Distribution

Distribute NCR within 24 hours to:

  • QA Manager
  • Construction Manager
  • Responsible subcontractor
  • Engineer's Representative (for critical and major NCRs)
  • Document Controller (for filing)

Step 3: Log NCR

Document Controller logs NCR in NCR Register:

  • NCR number
  • Date raised
  • Category and type
  • Responsible party
  • Status (Open/In Progress/Closed)
  • Target closure date

6.3 Investigation and Root Cause Analysis

Step 1: Investigate

Construction Manager and responsible subcontractor investigate:

  • How did the non-conformance occur?
  • When was it introduced?
  • How many units/locations are affected?
  • Why was it not caught earlier?
  • What are the potential impacts?

Step 2: Root Cause Analysis

For critical and major NCRs, perform root cause analysis using "5 Whys" technique:

Example:

  • Problem: String insulation resistance test failed (reading 0.2 MΩ, required >1 MΩ)
  • Why 1: Why did the test fail? Water ingress in connector
  • Why 2: Why was there water ingress? Connector not properly sealed
  • Why 3: Why was connector not sealed? Installer did not push connector fully home
  • Why 4: Why didn't installer push fully? Not aware of correct installation technique
  • Why 5: Why not aware? Insufficient training on connector installation
  • Root Cause: Lack of training on proper DC connector installation

Step 3: Document Findings

Complete Section D of NCR Form:

  • Investigation findings
  • Root cause determination
  • Extent of non-conformance (how many similar instances exist?)

6.4 Corrective Action Plan

Step 1: Propose Corrective Action

Responsible party proposes corrective action:

OptionDescriptionWhen Used
RepairFix the non-conforming work to meet requirementsMost common for installation defects
ReworkRemove and redo the workWhen repair is not feasible
ReplaceReplace non-conforming materialsFor defective materials
ConcessionAccept non-conformance with approved deviationOnly if performance not affected (requires Engineer approval)
RejectReturn materials or demolish workWhen correction not possible or economical

Step 2: Document Corrective Action

Complete Section E of NCR Form:

  • Proposed corrective action method
  • Procedure/method statement for correction
  • Responsible person
  • Target completion date
  • Resources required
  • Testing/verification method after correction

Step 3: Approval

NCR CategoryApproval Required
CriticalQA Manager AND Engineer's Representative
MajorQA Manager
MinorQC Inspector

Note: Any concession (accept-as-is) requires Engineer's Representative approval regardless of category.


6.5 Implementation of Corrective Action

Step 1: Execute Correction

Responsible party implements approved corrective action:

  • Follow approved method statement
  • Use qualified personnel
  • Maintain safety standards
  • Document the correction process with photos

Step 2: Notify QC for Verification

Upon completion, responsible party notifies QC Inspector that correction is complete and ready for verification.

Step 3: Verification Inspection

QC Inspector verifies corrective action:

  • Inspect corrected work against original requirements
  • Conduct any required re-testing
  • Take photos of corrected work
  • Complete Section F of NCR Form (Verification)

Verification Results:

  • Accepted: Corrective action effective, non-conformance resolved
  • Rejected: Corrective action ineffective, further action required (NCR remains open)

6.6 Preventive Action

Step 1: Identify Preventive Measures

To prevent recurrence, identify preventive actions:

Examples:

  • Additional training for workforce
  • Update work instructions or procedures
  • Improve inspection methods
  • Change material supplier
  • Implement additional checks or controls
  • Modify construction sequencing

Step 2: Document and Implement

Complete Section G of NCR Form:

  • Preventive action description
  • Responsible person
  • Implementation date
  • Verification method

Step 3: Verify Effectiveness

QA Manager verifies preventive actions are implemented and monitors for recurrence.


6.7 NCR Closure

Step 1: Closure Approval

Once corrective action verified and preventive actions implemented:

NCR CategoryClosure Approval
CriticalQA Manager AND Engineer's Representative
MajorQA Manager
MinorQC Inspector

Step 2: Update NCR Register

Document Controller updates NCR Register:

  • Status changed to "Closed"
  • Closure date recorded
  • Closure approval noted

Step 3: File Documentation

File complete NCR package including:

  • Original NCR form
  • Investigation notes
  • Photos (before and after)
  • Test results (if applicable)
  • Approvals
  • Corrective action records

Target Closure Times:

  • Critical NCR: Within 7 days
  • Major NCR: Within 30 days
  • Minor NCR: Within 14 days

7. NCR Tracking and Reporting

7.1 NCR Register

Document Controller maintains NCR Register with:

  • NCR number and date
  • Category and type
  • Description (brief)
  • Responsible party
  • Status (Open/In Progress/Closed)
  • Date closed
  • Days open

7.2 Monthly Reporting

QA Manager provides monthly NCR report to Project Manager including:

  • Total NCRs raised (by category and type)
  • NCRs closed during period
  • Open NCRs (status update)
  • Overdue NCRs (action required)
  • Trend analysis (are NCRs increasing/decreasing?)
  • Common themes (systemic issues)
  • Recommendations

7.3 Trend Analysis

QA Manager analyzes NCR data to identify:

  • Recurring issues (same non-conformance repeated)
  • Problematic subcontractors (high NCR rates)
  • Problem areas (specific discipline or activity)
  • Effectiveness of preventive actions

Trends are reviewed in monthly quality meetings and corrective actions implemented.


8. Special Cases

8.1 Client-Issued NCRs

When client issues an NCR to contractor:

  • Treat as critical (unless stated otherwise)
  • Response required within 48 hours
  • Corrective action plan within 5 days
  • Regular status updates to client
  • Formal closure approval from client required

8.2 Systemic Non-Conformances

When multiple similar NCRs occur (3 or more of same type):

  • Escalate to QA Manager and Construction Manager
  • Conduct comprehensive root cause analysis
  • Implement systemic corrective actions
  • May require procedure revision or re-training
  • Increased inspection frequency until resolved

8.3 Repeated Non-Conformances

When same non-conformance recurs after corrective action:

  • Indicates ineffective corrective action
  • Re-open investigation
  • Consider alternative corrective approach
  • May require subcontractor performance review
  • Escalate to Project Manager

9. Non-Conformance Examples (Learning Reference)

Example 1: Material Non-Conformance

NCR-045: PV Modules with Cell Cracks

  • Description: During receiving inspection, 15 modules found with hairline cell cracks (5% of delivery)
  • Category: Major
  • Root Cause: Inadequate packaging for transport
  • Corrective Action: Rejected and returned to supplier, replacement delivery with improved packaging
  • Preventive Action: Updated receiving inspection to check 10% sample (increased from 5%), supplier to use reinforced packaging

Example 2: Installation Non-Conformance

NCR-078: Tracker Foundation Piles Below Minimum Depth

  • Description: 12 piles in Row 15 installed to 1.2m depth (specification requires minimum 1.5m)
  • Category: Critical (structural integrity)
  • Root Cause: Installer did not verify depth measurement, assumed torque alone was sufficient
  • Corrective Action: Extract and reinstall all affected piles to correct depth, re-test torque
  • Preventive Action: Mandatory depth measurement for every pile (100%), daily toolbox talk on pile installation requirements

Example 3: Testing Non-Conformance

NCR-102: String Insulation Resistance Below Minimum

  • Description: String S-045 insulation resistance = 0.3 MΩ (requirement ≥1 MΩ)
  • Category: Major
  • Root Cause: Moisture ingress in one DC connector due to improper mating
  • Corrective Action: Identified faulty connector, replaced, re-tested (result: 150 MΩ - pass)
  • Preventive Action: Re-training on DC connector installation, implement "click test" verification (pull test after connection)

Example 4: Documentation Non-Conformance

NCR-125: Missing Material Certificates

  • Description: HV cable installed without required continuous length certificates
  • Category: Major
  • Root Cause: Cable drum delivered without certificates, installer proceeded without verification
  • Corrective Action: Obtain certificates from supplier (verified cable drum was continuous length), retroactively approved
  • Preventive Action: Updated procedure - no cable installation without certificates present on site

10. Forms and Templates

10.1 Required Forms

  • Form QF-002: Non-Conformance Report (NCR)
  • NCR Register Template: Excel tracking spreadsheet
  • Monthly NCR Summary Report Template

10.2 NCR Numbering System

Format: QAR-NCR-[Year]-[Sequential Number]

Example: QAR-NCR-2025-045

  • QAR = Qaremy Construction
  • NCR = Non-Conformance Report
  • 2025 = Year
  • 045 = 45th NCR of the year

11. Training Requirements

All project personnel must receive training on:

  • How to identify non-conformances
  • How to report non-conformances
  • Immediate actions when NC identified
  • NCR process and responsibilities
  • Importance of corrective and preventive action

Training recorded in project training register.


12. References

  • AS/NZS ISO 9001:2016 - Quality Management Systems (Clause 10: Improvement)
  • QAR-QMP-001 - Quality Management Plan
  • All Inspection and Test Plans (ITPs)
  • Project specifications and standards

13. Appendices

  • Appendix A: Form QF-002 - Non-Conformance Report
  • Appendix B: NCR Register Template
  • Appendix C: Root Cause Analysis Tools (5 Whys, Fishbone Diagram)
  • Appendix D: Monthly NCR Report Template

14. Revision History

RevisionDateDescriptionPrepared ByApproved By
AOct 2025Initial IssueQA ManagerProject Manager

END OF DOCUMENT